Reference-list of GIPROKOKS main projects since 1999


No.

Client

Start-up

Design capacity of gross coke, thous.t/year

No. of ovens

Oven volume, m3

Oven dimensions, mm

Heating system

Ukraine

1.

PJSC "Kharkivskiy COP
Construction of COB No.4-bis

28.06.2006

160

25

24,6

13120x4300x500;
50

PVR, c.o.g., gunflue

2.

PJSC "Kharkivskiy COP
Pad-up Rebuilding of COB No. 1- bis (with coal handling and by-product plant)
Option 1. Stamp charging
Option 2. Top charging

Technical and economic feasibility

143
118

29

24,6

13120x4300x500;
40

PVR, c.o.g., gunflue

3.

PJSC “AzovStal”
Pad-up Rebuilding of COB No.3

16.04.2003

455

65

20,0

13020х4300х410;
50

PVR, compound, gunflue

4.

PJSC “AzovStal”
Pad-up Rebuilding of COB No.4

29.03.2006

455

65

20,0

13020x4300x410; 50

PVR, compound, gunflue

5.

PJSC “AzovStal”
Construction of COB No. 2-bis

Construction in progress

910

65

41,3

15860x7000x410;
50

PVR, compound, underjet

6.

LLC “ISTEK” (Gorlovsky COP)
Pad-up Rebuilding of COB No.3

13.12.2005

466

57

23,5

13120х5000х410;
50

PVR, c.o.g., gunflue

7.

LLC “ISTEK” (Gorlovsky COP)
Pad-up Rebuilding of COB No.4

Designing completed

485

58

24,3

13120x5000 x420; 40

PVR, c.o.g., gunflue

8.

PrJSC “Evraz Uzhkoks”
Pad-up Rebuilding of COB No.7

29.07.2008

490

65

21,6

13980x4300x410;
50

PVR, c.o.g., gunflue

9.

РJSC "ArcelorMittal Kryvyi Rih"
Pad-up Rebuilding of COB No.4
(with by-product plant reconstruction)

18.01.2007

550

56

30,7

13980x6000x410;
50

PVR, c.o.g., gunflue

10.

РJSC "ArcelorMittal Kryvyi Rih"
Pad-up Rebuilding of COB No.3

27.12.2007

550

56

30,7

13980x6000x410;
50

PVR, c.o.g., gunflue

11.

РJSC "ArcelorMittal Kryvyi Rih"
Pad-up Rebuilding of COB No.5,6
(with stamp charging of coal blend)

Construction in progress

1060

114=57+57

35,8

15900x5000x500;
20

PVR, c.o.g., gunflue

12.

PJSC "Yasinovsky COP"
Pad-up Rebuilding of COB No.1

13.07.2006

450

61

21,6

13980x4300x410;
50

PVR, c.o.g., gunflue

13.

PJSC "Yasinovsky COP"
Pad-up Rebuilding of COB No.6

25.06.1999

690

77

29,8

14940x5000x450;
50

PVR, c.o.g., gunflue

14.

PJSC "Yasinovsky COP"
Pad-up Rebuilding of COB No.5

15.12.2002

690

77

29,8

14940x5000x450;
50

PVR, c.o.g., gunflue

15.

PrJSC “Avdeevskiy COP”
Pad-up Rebuilding of COB No. 3

24.01.2008

690

77

30

15040x5000x450;
40

PVR, c.o.g., underjet

16.

PrJSC “Avdeevskiy COP”
Pad-up Rebuilding of COB No.4
(with by-product plant reconstruction)

Construction is underhold

690

77

30

15040x5000x450;
40

PVR, c.o.g., underjet

17.

PJSC "Zaporozhkoks"
Pad-up Rebuilding of COB No. 1-bis

Designing completed

800

65

42,9

15860x6650x450;
50

PVR, c.o.g., underjet

18.

PJSC "Zaporozhkoks"
Construction of CDCP (2 х 70 t/h)

Designing completed

19.

PJSC "Alchevskkoks"
Construction of COB No.10-bis
(with stamp charging of coal blend)

26.10.2006

1000

113

35,8

15900x5000x500;
20

PVR, c.o.g., gunflue

20.

PJSC "Alchevskkoks "
Construction of CDCP (3 х 70 t/h)

2007

21.

PrJSC "Makeevkoks"
Retrofitting of Plant for coke oven gas purification from hydrogen sulphide

2012

22.

PrJSC «Enakievskiy coke oven and by-product plant»
Construction of WWTS

Designing completed

Russian Federation

23.

JSC "Mechel-Koks”
Pad-up Rebuilding of COB No. 6

18.03.2011

470

61

21,6

13980x4300x410;
50

PVR, c.o.g., gunflue

24.

PJSC "Severstal" (Cherepovets Steel Mill)
Pad-up Rebuilding of COB No.3
(with two CDCP blocks and by-product plant No.1 rebuilding)

25.10.2006

460

61

21,6

13980x4300x410;
60

PVR, compound, gunflue

25.

PJSC "Severstal"
Pad-up Rebuilding of COB No.4
(with by-product plant No.1 rebuilding)

Designing completed
Wet quenching complex - 2015

460

61

21,6

13980x4300x410;
60

PVR, compound, gunflue

26.

PJSC "Severstal"
Pad-up Rebuilding of COB No.7
(with three CDCP blocks and by-product plant No.2 rebuilding)

01.04.2013

700

65

32,1

15900x5500x410;
60

PVR, c.o.g., underjet

27.

PJSC "Severstal"
Pad-up Rebuilding of COB No.8 (with by-product plant No.2 rebuilding

Designing completed

700

65

32,1

15900x5500x410;
60

PVR, c.o.g., underjet

28.

OJSC "Gubakhinskiy Coke"
Pad-up Rebuilding of COB No.2-bis

02.2002

650

65

30,9

14080x6000x410;
50

PVR, c.o.g., gunflue

29.

OJSC "Gubakhinskiy Coke"
Pad-up Rebuilding of COB No.1-bis

01.02.2011

650

65

30,9

14080x6000x410;
50

PVR, c.o.g., gunflue

30.

OJSC "UralSteel"
Reconstruction of COB No.6 with CDCP

2014

690

65

30,3

15040x5500x410;
50

PVR, c.o.g., gunflue

31.

OJSC "EVRAZ ZSMK"
Pad-up Rebuilding of COB No.1

22.12.2005

750

77

35,5

14940x5500x480;
50

PVR, c.o.g., gunflue

32.

PJSC "Koks"
Pad-up Rebuilding of COB No.6

14.05.2001

650

65

30,7

13980x6000x410;
40

PVR, c.o.g., gunflue

33.

PJSC "Koks"
Pad-up Rebuilding of COB No.5 with CDCP

Designing completed

780

65

42,9

15860x6650x450;
50

PVR, c.o.g., gunflue

34.

PJSC "Koks"
Construction of COB No.3

27.04.2007

850

71

42,9

15860x6650x450;
50

PVR, c.o.g., gunflue

35.

PJSC “Novolipetsk Steel” (NLMK)
Pad-up Rebuilding of COB No.1

25.09.2005

460

61

23,7

13980x4700x410;
50

PVR, c.o.g., gunflue

36.

PJSC “Novolipetsk Steel” (NLMK)"
Pad-up Rebuilding of COB No.2

31.01.2007

460

61

23,7

13980x4700x410;
50

PVR, c.o.g., gunflue

37.

PJSC “Novolipetsk Steel” (NLMK)
Pad-up Rebuilding of COB No.5

01.03.1999

810

77

35,2

15900x5500x450;
50

PVR, c.o.g., gunflue

38.

PJSC “Novolipetsk Steel” (NLMK)
Pad-up Rebuilding of COB No.6

01.03.2000

810

77

35,2

15900x5500x450;
50

PVR, c.o.g., gunflue

39.

PJSC “Novolipetsk Steel” (NLMK)
By-product plants Nos.1&2 modernization
WWTS construction
Combined by-product plant


2007
2014
Construction in progress

40.

OJSC "Magnitogorsk Iron & Steel Works"
Pad-up Rebuilding of COB No.1

01.10.1999

613

56

30,9

14080x6000x410;
50

PVR, compound, gunflue

41.

OJSC "Magnitogorsk Iron & Steel Works"
Construction of COB No.11-bis

Construction in progress

1140

41x2=
82

51

16820x7000x480;
50

PVR, compound, underjet

42.

OJSC "Altai-Koks "
Construction of COB No.5

10.10.2006

1140

41 x 2 = 82

51

16820x7000x480;
50

PVR, c.o.g., underjet

43.

OJSC "UralSteel"
Construction of coal tar processing complex

Designing completed

Arab Republic of Egypt

44.

Al Nasr Company for Coke and Chemicals
Pad-up Rebuilding of COB No.1

2000

372

50

21,6

14080x4300x410;
50

PVR, compound, gunflue

45.

Al Nasr Company for Coke and Chemicals
Pad-up Rebuilding of COB No.2

2006

372

50

21,6

14080x4300x410;
50

PVR, compound, gunflue

Italian Republic

46.

Lucchini Piombino SpA
Construction of COB No.1
(Technological khow-how,
BE - technology and equipment,
DE - refractory brickwork)

2002

430

45

32,7

13120x6200x450;
60

PVR, compound, gunflue

47.

ILVA Taranto (RIVA Group)
Reconstruction of COB No.10

Construction in progress

400,70

43

39,4

15800х6420х435;
64

PVR, compound, underjet

Islamic Republic of Pakistan

48.

Pakistan Steel Mills Corp.
Capital repair of COB No.1

Works completed

480

49

30,5

15160x5500x410;
40

PVR, c.o.g., underjet

49.

Pakistan Steel Mills Corp.
Capital repair of COB No.2

2008

480

49

30,5

15160x5500x410;
40

PVR, c.o.g., underjet

Republic of Turkey

50.

Iskenderun Iron & Steel Works Co.
Pad-up Rebuilding of COB No.4

2012

500

69

27,3

15040x5000x410;
40

PVR, compound, underjet

Federative Republic of Brazil

51.

Intendente Câmara Plant (USIMINAS)
Revamping of COB Nos. 3,4
(with quenching system and
by-product plant reconstruction)
COB No.3
COB No.4





2015
Designing
completed

550 x 2=
1100

55 x 2=
110

37,8

15500x6000x450;
60

PVR, compound, underjet

Republic of Poland

52.

KK Zabrze. Koksownia "Radlin"
Construction of COB No.1-bis
(with stamp charging technology)

2008

750

43 x 2 = 86

35,8

15900x5000x500;
40

PVR, c.o.g., underjet

53.

" Koksowni Częstochowa Nowa Spółka z o.o."
Construction of COB No. 1-bis
(with stamp charging technology)

2011

364

57

20,0

13170x3800x460;
20

PVR, c.o.g., gunflue

54.

" Koksowni Częstochowa Nowa Spółka z o.o."
Reconstruction of COB No. 4-bis
(with stamp charging technology)

Designing completed

308/239

50

27,9

13170x4300x560;
20

PVR, c.o.g., gunflue

Republic of Hungary

55.

ISD Dunaferr Zrt.
Rebuilding of COB No.3

stage I -2003
stage II- 2006

830

65

42,0

16130x7000x410;
50

PVR, c.o.g., underjet

56.

ISD Dunaferr Zrt.
Modernization of two blocks of CDCP for COB No. 3

Works completed

Islamic Republic of Iran

57.

Esfahan Steel Company
Construction of COB No.3 complex

2013

900

37 x 2 = 74

41,3

15860x7000x410;
50

PVR, compound, underjet

Republic of Kazakhstan

58.

JSC “ArcelorMittal Temirtau"
Pad-up Rebuilding of COB No.7

2006

910

65

41,3

15860x7000x410;
50

PVR, c.o.g., underjet

People's Republic of China

59.

Taiyuan Iron and Steel (Group) Company
Construction of Plant for hydrogen sulphide removal from coke oven gas
C.o.g. treatment capacity 130000 nm3/h
C.o.g. treatment capacity 65000 nm3/h




2008
2013

Republic of India

60.

Rourkela Steel Plant
Pad-up Rebuilding of COB No.1
(technical assistance to MECON)

2007

430

70

21,6

13590x4500x400;
60

PVR, compound, underjet

61.

Rourkela Steel Plant
Reconstruction of COB No. 3

Construction in progress

420/425

35 x 2=
70

21,6

13590х4500х400;
60

PVR, compound, underjet

62.

Rourkela Steel Plant
Construction of CDCP for COB No.6
(4 blocks х 50 t/h)

2013

63.

Bhilai Steel Plant
Pad-up Rebuilding of COB Nos.5,6


2009
2011

415,11

65

21,6

13980x4300x410;
50

PVR, compound, gunflue

64.

Bhilai Steel Plant
Construction of COB No.11

2014

881,4

67

41,6

16000x7000x410;
50

PVR, compound, underjet

65.

Bhilai Steel Plant
Construction of CDCP for COB No.11
(4 blocks х 50 t/h)

2014

66.

IISCO Steel Plant
Construction of COB No.11

2013

881,4

37x2=
74

41,3

15860x7000x410;
50

PVR, compound, underjet

67.

IISCO Steel Plant
Construction of CDCP for COB No.11
(4 blocks х 50 t/h)

2013

68.

NMDC Ltd .
Construction of COB Nos. 1,2 complex
with CDCP (2 х 4 blocks х 50 t/h)

Construction in progress

881,4 x 2=
1762,8

67 x 2= 134

41,6

16000x7000x410;
50

PVR, compound, underjet

69.

Visakhapatnam Steel Plant
Construction of COB No.5

Construction in progress

840

67

41,6

16000x7000x410;
50

PVR, compound, underjet

70.

Visakhapatnam Steel Plant
Construction of CDCP for COB No.5
(4 blocks х 50 t/h)

Construction in progress